Form13160-5 (September 2001) UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT OCD Hobbs SUNDRY NOTICES AND REPORTS ON WELLS Do not u
9:30 9:30 0.00 cementers. Had good returns through the job. Circulated 507 sks. (159) bbls. Of cement to surface. 9:30 9:30 0.00 Plug down @ 09:05 a
12/22/2012 6:00 7:00 1.00 TIH to 5141' 7:00 7:15 0.25 Kelly up and break circulation. 7:15 10:00 2.75 Wash f/5141' to 5226', tagge
12/24/2012 6:00 8:30 2.50 R/D 7 7/8" v/s f/7246' to 7373'. Wob 25/27, rpm 50, mmrpm 66, spp 1850, d/p 200/350, rop 50.8 fph. 8:30 8:
Diesel used 650 gals. Fuel on hand 7574 gals. 12/26/2012 6:00 6:00 24.00 Well shut in and secured for Christmas. Will resume operations @ 07:00 am th
2:45 5:00 2.25 BCS f/857678608'. (2.00) s/v (.25) @ 8556' inc. 23.77, az 178.15, dls 11.83, wob 18/40, mmrpm 126, 5:00 5:00 0.00 gpm 384
13:30 14:15 0.75 Install rotating head. Kelly up and wash one jt. To bottom. 14:15 16:15 2.00 m/d c/s f/886078892'. Wob 15/40, rt 30, mm 126, g
12/31/2012 6:00 7:00 1.00 m/d c/s f/930479319'. Wob 15/40, rt30, mm126, gpm397, spp1295.(.75) s/v-9256',inc.87.11, az182.52, dls17.95 7:00
Diesel used 1236 gals. Diesel on hand 6989 gals. 01/02/2013 6:00 7:00 1.00 Curve got tight @ 8930'. L/D 12 jts. Of DP out of the derrick. 7:00
23:00 0:45 1.75 p/d lat/s f/11,071711,166'. Wob 25, rt 50, mm 72, gpm 428, (1.50). s/v-11,132', inc. 90.69, az 178.71, dls 0.92 0:45 2:45 2
13:15 15:00 1.75 p/d lat/s f/12,971713,067'. Wob 30, rt 70, mm 72, gpm 426. (1.50). s/v-13,033', inc. 90.65, az 179.89, dls 0.25 15:00 16:3
GMT Exploration Company LLC Pryor Federal-State #4H Drilling Operations 12/03/2012 - 12/06/2012 6:00 6:00 0.00 12-3-12 MONDAY; START MIRU MCVAY. RIG
13:00 15:00 2.00 Break out logging tools from reamer and l/d logging tools. Catch ball on logging tool is 2 3/8". 15:00 15:00 0.00 Break down T
« > < 01/09/2013 6:00 9:00 3.00 Held PJSM with Man Services N/D crew. Install stack lifts. N/D BOP, manifold, flowline. 9:00 10:00 1.00 Lift sta
Should have all the last of the cost recorded on Friday. Youngs final invoices and Mico final invoices. Diesel used 200 gals. Diesel on hand 2652 gals
Pryor #4H Frac Treatment Summary Depths Water Pumped Bbls. 40/70 Sand lbs 20/40 Sand lbs. Total Sand lbs. Stage 1 13181'-13481' 8,214 96,057
6:00 8:30 2.50 WOC 8:30 9:15 0.75 TIH and tag cement @ 98'. 9:15 9:30 0.25 P/U kelly and break circulation. 9:30 11:00 1.50 Drill cemen
12/10/2012 6:00 7:00 1.00 Drill 171/2" Surface section f/1820' to 1850'. TD surface section. 7:00 9:00 2.00 Pump two sweeps and circula
12/12/2012 6:00 9:00 3.00 Run 13 3/8" casing to 1809'. 45 jts. Of 13 3/8" 54# J-55 ST&C casing. 9:00 11:30 2.50 Swedge up on jt 46
this morning. Diesel used 744 gals. Fuel on hand 8522 gals. 12/14/2012 6:00 8:15 2.25 Drlg. 12 1/4" intermediate section f/1899' to 1994&ap
1 1 Diesel used 2146 gals. Fuel on hand 6376 gals. 12/15/2012 6:00 8:00 2.00 Drlg. 12 1/4" intermediate section f/3025' to 3195'. Surv
Diesel used 1802 gals. Fuel on hand 2522 gals. 12/17/2012 6:00 8:00 2.00 Continue to POOH. Found that we were 30' deeper than reported 4333&apo
5:00 6:00 1.00 Drlg. 12 1/4" intermediate section f/5237' to 5242'. Drlg. w/40K WOB @ 5 FPH. Will TD @ 5267'-5270' for best